The three-month plan

The programme that turns the Stop · Go · Build decision into sequenced work: three tracks running in parallel, a small number of hard dependencies between them, and a gate at every point where one track releases another. This page is the starting-point plan — the shape and the dependencies are settled; squad allocation and calendar dates need Leadership.

The three tracks

The dependency map

Three dependencies do most of the sequencing work:

  1. STOP exit gates unblock rebuilds. No product enters the RAPID pipeline until it passes Definition of Stable — you cannot safely point agents at an unstable estate. StudyBuddy goes first, so its remediation, DORA baseline and knowledge pack are the STOP track's earliest priority.
  2. The minimum-viable toolkit gates the StudyBuddy build. Definition and Design can start on drafts, but the Build phase does not start until the checklist below passes — otherwise the pilot proves improvisation, not the pattern.
  3. StudyBuddy proves the pattern before CXsmart. Applying RAPID to a bigger product is an explicit go/no-go at the CXsmart scale-up gate, decided on pilot-charter evidence — not on enthusiasm.

The minimum-viable toolkit

The checklist GO must complete before StudyBuddy's Build phase starts. Owned by the Toolkit Guild; deliberately minimal — everything else can be built while the pilot runs:

  • Gate cards live for the pipeline transitions — Definition of Ready through Production Readiness.
  • Definition artefacts ready — the PFD template and the task-brief prompt proven on at least one dry run.
  • Guardrails enforced in the scaffoldagent guardrails, secrets management and the CI/CD standard wired into the RAPID project scaffold, not documented beside it.
  • Metrics instrumented — the four DORA keys captured automatically from day one of the rebuild (metrics platform).
  • Squad onboarded — the StudyBuddy squad through onboarding with agent access, budgets and permissions in place.

Month by month — skeleton

Month boundaries are placeholders until Leadership sets dates; the sequencing within each track is the commitment.

MonthSTOPGOBUILDSquads
1Client-commitment triage; tech-debt, security-gap and ways-of-working audits; FinOps review; StudyBuddy remediation prioritisedTooling evaluation; gate cards and core templates drafted; scaffold v1StudyBuddy DORA baseline and legacy knowledge pack; Definition startsTBD
2Remediation sprints; secrets sweep complete; StudyBuddy (and first wave) through Definition of StableMinimum-viable-toolkit checklist passed; squad shapes agreed; metrics platform liveDesign and Tech selection; Build starts once the toolkit checklist passesTBD
3Remaining products through STOP exit or dispositioned via the portfolio frameworkGuild rhythm running; toolkit gaps from the pilot's friction log closedRefinement; first Flow-state ⇄ Production turns; operating-model retro; CXsmart scale-up gateTBD
Needs Leadership

Squad allocation across the three tracks, calendar start/finish dates for each month block, and which products join StudyBuddy in the first Definition-of-Stable wave are Leadership decisions. The TBD markers stay until they are made — this plan sequences the work; it does not staff it.

Standards referenced: DORA (baseline and before/after delta).